Jordan's Grove Road Project Update

The bridge replacement project on Jordans Grove Road was let on March 19, 2019 and the project was awarded to A.M. Cohron & Sons, Inc. of Atlantic, Iowa for a cost of $1,969,450.47. The bridge is over the Wapsipinicon River and a project schedule is not known at this time.

Facebook Twitter Email

Latest Update:

July 10, 2020 10:04 AM

With the heavy rain the last several weeks the river levels wwere high and flooded the project site. The contractor was unable to work the past several weeks. The contractor has resumed work, but the completion date has been pushed back to late September or early October.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

Prior Updates

June 19, 2020 9:06 AM

Work continues to progress on the bridge replacement project. The contractor just poured a portion of the bridge deck earlier this week. The project is on schedule to be completed by August.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

May 28, 2020 6:50 AM

Work continues to progress on the bridge replacement project. The contractor is currently working on the last pier. The project is on schedule to be completed by July or August.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

May 11, 2020 9:36 AM

Work continues to progress on the bridge replacement project. The contractor has placed the beams for on the south half of the bridge. The project is on schedule to be completed by July or August.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

February 10, 2020 1:01 PM

Work continues to progress on the bridge replacement project. The contractor is placing concrete today for the footing of the middle pier. The project is on schedule to be completed by September.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

January 9, 2020 6:59 AM

The bridge replacement project has been underway for about 1 month and is still on schedule to finish by September. The contractor is currently removing the old bridge and is building temporary rock platforms in order to work in the river.

Please contact me if you have any questions.

Garret Reddish (garret.reddish@linncounty.org)

December 4, 2019 1:15 PM

The bridge replacement projected start on Monday December 2nd as planned. The project is expected to last 7-9 months and should be completed by September. There will not be a lot of project updates throughout construction. If you have questions please feel free to contact me. Thank you for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)

November 27, 2019 7:44 AM

As a reminder, the contractor plans to start on Monday December 2nd. The project is expected to last 7-9 months and should be completed by September. Jordan's Grove Road will be closed at this location for the duration of the project. There will be a posted detour utilizing Waubeek Road, Boys Scouts Road, and Sawyer Road.

Please contact me with any questions. Thank you for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)

November 18, 2019 6:49 AM

The contractor, A.M. Cohron & Sons, is scheduled to start on Monday December 2nd. The project is expected to last 7-9 months and should be completed by September.
Jordan's Grove Road will be closed at this location for the duration of the project. There will be a posted detour utilizing Waubeek Road, Boys Scouts Road, and Sawyer Road.

Please contact me with any questions. Thank you for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)

May 3, 2019 8:39 AM

The contractor plans to start construction this fall. They want to mobilize in late September or early October. The project is expect to be completed in April or May 2020.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

May 3, 2019 8:39 AM

The contractor plans to start construction this fall. They want to mobilize in late September or early October. The project is expect to be completed in April or May 2020.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

May 3, 2019 8:39 AM

The contractor plans to start construction this fall. They want to mobilize in late September or early October. The project is expect to be completed in April or May 2020.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)