East Post Road Paving

◄ Back
February 11, 2019 2:17 PM

East Post Road Project Update

The project was let on March 12, 2019 and the project was awarded to L.L. Pelling of North Liberty, Iowa for a cost of $327,646.13. The paving limits are from Fox Meadow Drive north to Cottage Grove Woods. As per the contract, the late start date for the project is August 12, 2019. This means the contractor may begin on or before that date. The contractor will be allowed 25 working days to complete the project. Once started, the project will take approximately 4-6 weeks for completion. An exact start date has not been determined yet.

Facebook Twitter Email

Latest Update:

June 7, 2019 6:53 AM

The contractor finished the pavement markings yesterday and the project is now complete. Thank you for your cooperation!

Garret Reddish (garret.reddish@linncounty.org)

Prior Updates

View All Updates
June 4, 2019 9:18 AM

The pavement markings are scheduled to be painted on Thursday (6th). Once painted, the project will be complete.

Please contact me with any questions. Thank you for your cooperation!

Garret Reddish (garret.reddish@linncounty.org)

May 31, 2019 6:54 AM

The contractor worked yesterday, but did not finish. They expect to finish all the driveway work today. The last remaining items are rock shoulders and pavement markings. The project is expected to be completed early next week with good weather.

Please contact me with any questions. Thanks for your cooperation!

Garret Reddish (garret.reddish@linncounty.org)