While all repairs and mitigation are not yet complete, the Linn County Correctional Center reopened in May 2009. Linn County is working with FEMA on mitigation and improvements that will reduce the severity of damages should there ever be another flood of the magnitude of 2008.
In January 2010, the Board of Supervisors reviewed a proposal to make improvements to the Linn County jail including building a three-story addition on the south side of the building. The improvements and addition (referred to as Phase II) would fulfill multiple needs at the jail and the Courthouse.
The driving force of Phase II is mitigation. Highlights of the plan include elevating mechanical and electrical equipment that powers the jail and the Courthouse to an upper level to protect the equipment in the event of another flood. The jail's laundry room will also be moved to an upper level as part of the mitigation. In its place, isolation cells will be constructed on the main level. Other improvements include expanding the jail's kitchen to improve efficiency. When the jail was built in 1984, it was designed for 135 inmates and the kitchen was designed to serve that number. The capacity of the jail has now grown to 409 inmates and the kitchen design has not kept up with the increase in capacity. Expanding the kitchen would create more efficiencies in its operation.
The plan also includes converting the jail's two main hydraulic elevators to traction control elevators. Traction elevators are operated by counter-weights and are faster than hydraulic elevators and require less maintenance. A traction elevator will be protected from future flooding because the mechanics of a traction elevator are not located in the lowest level of the building as they are with hydraulic elevators. With the increased capacity of the jail, traction control elevators will allow deputies and jail staff to move inmates and supplies more efficiently.
The improvements at the jail are considered an improved project by FEMA. Linn County anitcipates $3.5 million from FEMA for flood-related repairs at the jail in this Phase II project. Linn County will bond for $4.1 million.
Total Cost: $7.6 million Completion Date: 2012 Architect: Aspect, Inc. General Contractor: Miron Construction Funding Sources: $3.5 million FEMA $4.1 million Linn County bonding Mitigation:
- Elevate mechanical and electrical equipment
- Move laundry room to an upper level
- Convert hydraulic elevators to traction control elevators
|
|