Edgewood Rd Project: Tower Terrace to County Home

1 Alert
June 1, 2017 1:35 PM

Edgewood Road Project Update

Concrete paving project from a point a half mile north of Tower Terrace Road to County Home Road. The project is tentatively scheduled a March 6, 2018 letting. As per the contract, the late start date for the project is June 4, 2018. The contractor will...

Read On...

Latest Update:

June 21, 2018 11:52 AM

The contractor is not paving concrete today due to the rain. They are "on call" to pave tomorrow if the weather cooperates, but looking at the forecast they don't expect to pave. They will not be paving over the weekend and they plan to pave on Monday. They did perform some asphalt paving today at a few of the intersections. More asphalt paving will occur as construction progresses and as weather allows.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

Lewis Access Road: Cedar River Bridge to I-380

1 Alert
April 12, 2017 7:17 AM

Lewis Access Road Project Update

Concrete paving project on Lewis Access Road from the Cedar River bridge to the I-380 overpass. The project is tentatively scheduled for a March 6, 2018 letting. More project details will be provided once the contract is awarded.

Latest Update:

June 13, 2018 9:07 AM

This is not a new update, just repeat information for new subscribers. The project has been awarded to Croell, Inc. of New Hampton, Iowa for the price $873,932.13. The contractor tentatively plans to start construction in mid/late July. Construction is expected to take approximately 6-8 weeks. More details will become available as construction nears.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

Milburn Road: Blairs Ferry Rd to Tower Terrace Rd

1 Alert
April 23, 2018 7:16 AM

Milburn Road Project Update

The asphalt overlay project on Milburn Road was let on March 27, 2018 and was awarded to L.L. Pelling of North Liberty, Iowa for a cost of $574,364.08. The contract specifies a late start date of August 13, 2018 but an exact start date has not been...

Read On...

Latest Update:

June 22, 2018 7:47 AM

As a reminder, the contractor plans to start paving on Monday June 25th, weather permitting.

Please contact me if you have any questions.

Garret Reddish (garret.reddish@linncounty.org)

N Center Point Road & Spencers Grove Road Paving

1 Alert
April 11, 2018 12:39 PM

N Center Point Rd & Spencers Grove Rd Update

The project was awarded to Croell, Inc. of New Hampton, Iowa at the cost of $3,559,007.46. The contractor plans to start construction in late June and work is expected to take approximately 10-12 weeks. More details will become available as construction...

Read On...

Latest Update:

June 13, 2018 9:10 AM

The bridge on Spencer's Grove Road is complete. The culvert replacement on Spencer's Grove Road immediately west of the bridge is currently underway. That project is expected to be completed by the first week in July (2nd-6th). The paving project on Spencer's Grove Road and N Center Point Road is expected to start in mid-July. More details will be available as construction nears.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

Road Construction Updates

1 Alert
August 24, 2017 9:02 AM

Road Construction In Linn County

Road construction is starting in Linn County . If interested in project updates, please go to http://www.linncounty.org/list.aspx and subscribe to the specific project update list.

Please contact me with any questions.

Garret Reddish...

Read On...

Latest Update:

June 22, 2018 8:09 AM

Asphalt paving on Milburn Road from Blairs Ferry Road to Tower Terrace Road is expected to start on Monday June 25th. Please subscribe to that project update list to receive additional project details.

Garret Reddish (garret.reddish@linncounty.org)

Sawyer Road Bridge Replacement

1 Alert
November 22, 2017 12:49 PM

Sawyer Road Bridge Project:

The project for a 40'x100' continuous concrete slab bridge was let on November 21, 2017. The contract was awarded to Jim Schroeder Construction, Inc. of Bellevue, Iowa for a cost of $540,927.93. A schedule has not been submitted by the Contractor to...

Read On...

Latest Update:

May 14, 2018 7:39 AM

The project is progressing on schedule and is expected to be completed in early July. Sawyer Road will remain closed to all traffic at the bridge location.

Please contact me with any questions. Thank you for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)

Seal Coat: Various Locations in Linn County

0 Alerts
There are currently no alerts for this category.

Shellsburg Road & Blairs Ferry Road Paving Project

1 Alert
June 4, 2018 8:24 AM

Shellsburg Rd & Blairs Ferry Rd Project Update

The concrete paving project on Shellsburg Road and Blairs Ferry Road will be let on June 12, 2018. Construction includes concrete paving over the existing surface with granular shoulders. A construction schedule has not been determined yet, but is...

Read On...

Latest Update:

June 13, 2018 9:16 AM

The concrete paving project on Shellsburg Road, Blairs Ferry Road, and Hollenbeck Road was let on June 12th and has been awarded to Croell, Inc. of New Hampton, Iowa for the price $1,563,956.50. The contractor tentatively plans to start construction in mid to late July. Construction is expected to take approximately 10-12 weeks. Traffic is expected to remain open on Shellsburg Road, but Blairs Ferry Road and Hollenbeck Road will be closed during construction. More details will become available as construction nears.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

Spencer's Grove Road Bridge Replacement

1 Alert
November 22, 2017 12:47 PM

Spencer's Grover Road Bridge Project:

The project for a 40'x80' continuous concrete slab bridge was let on November 21, 2017. The contract was awarded to Jim Schroeder Construction, Inc. of Bellevue, Iowa for a cost of $527,219.65. The project will take approximately 4 months to complete. ...

Read On...

Latest Update:

June 13, 2018 9:03 AM

The contractor plans to complete the culvert replacement project by the first week in July (2nd-6th). The road will remain closed to all traffic at the culvert location.

Thank you for your cooperation. Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)